Milestones
Milestones are clean points where FX could be shipped. A milestone contains no P1 or P2 issues. Committers are encouraged to hold back significant changes just before a milestone to maximize stability.
Milestones occur at roughly 6 week intervals, starting and ending on a Tuesday. Extra emphasis is placed on testing the week before a milestone and on the Monday of the milestone.
Major Work Items:
- Accessibility
- Spinner, Formatted Text, Alert Dialogs
- RichTextEditor prototype
M1: Aug 4, 2014
- Reduce bug count
- Fix critical bug deferred from 8 and 8u20
- Accessibility work (xxx)
- Spinner completed
- Formatted text completed
- Alert Dialogs work (xxx)
M2: Sept 15, 2014 [FF]
- Reduce bug count
- Fix critical bug deferred from 8 and 8u20
- Accessibility completed
- Alerts Dialogs completed
- xxx
M3: Sept 16 - Oct 20, 2014
- Reduce bug count
- RichTextEditor prototype
- xxx
M4: Dec 1, 2014
- Reduce bug count
- RichTextEditor prototype
- xxxx
ZBB: Dec 9, 2014