Milestones | JIRA ID | Owner | Target Completion | Actual Finish Date | Comments |
Primitive rendering complete | Oracle/JetBrains | 21 Feb | Remaining tasks that are being worked upon- XOR Composite Rendering Hints Anti-aliased rendering | ||
Image rendering complete | JetBrains | 21 Feb | Still work in progress | ||
Text rendering complete | Oracle | 06 Mar | Grayscale Text Rendering is complete. LCD Text rendering is being worked upon. | ||
1st early access ready | Oracle/JetBrains | TBD | |||
IDE performance | JetBrains | TBD | |||
Execute JTREG tests and match current passrate | Oracle |
| Metal pipeline should pass all the same jtreg tests as OpenGL : i.e. no functional regressions | ||
Pass all JCK tests | Oracle | ||||
Functional complete with performance | Oracle/JetBrains | ||||
2D Alias Review Start | Oracle/JetBrains | Lanai does not require reviews before pushing. Once we are functional complete, we should start reviews of the code to make sure it conforms to style/quality/etc expectations, as well as reviewing the code for correctness, robustness etc. |
...