Milestones occur at roughly 6 week intervals, starting and ending on a Tuesday. Extra emphasis is placed on testing the week before a milestone and on the Monday of the milestone.
Major Work
...
Items:
- Accessibility
- Spinner, Formatted Text, Alert Dialogs
- RichTextEditor prototype
M1: July 1 -
- Reduce bug count
- Fix critical bug deferred from 8 and 8u20
- Accessibility work (xxx)
- Spinner prototype work
- Formatted Text prototype work
- Alert dialogs work (xxx)
- xxxx
...
Aug 4, 2014
- Reduce bug count
- Fix critical bug deferred from 8 and 8u20
- Accessibility work (xxx)
- Spinner completecompleted
- Formatted text completecompleted
- Alert dialogs Dialogs work (xxx)
M2: Aug 5 - Sept 15, 2014 [FF]
- Reduce bug count
- Fix critical bug deferred from 8 and 8u20
- Accessibility completecompleted
- Alerts dialogs completeDialogs completed
- xxx
M3: Sept 16 - Oct 20, 2014
- Reduce bug count
- Rich Text Editor RichTextEditor prototype
- xxx
M4: Oct 21 - Dec 1, 2014
- Reduce bug count
- xxxx
ZBB: Dec 9, 2014