Milestones occur at roughly 6 week intervals, starting and ending on a Tuesday. Extra emphasis is placed on testing the week before a milestone and on the Monday of the milestone.
Work Starts: July 1, 2014
- Reduce bug count
- Fix critical bug deferred from 8 and 8u20
- Accessibility work (xxx)
- Spinner prototype work
- Formatted Text prototype work
- New Controls work (xxx)
- xxxx
M1: Aug 4, 2014
- Reduce bug count
- Fix critical bug deferred from 8 and 8u20
- Accessibility work (xxx)
- Spinner complete
- New Controls work (xxx)
M2: Sept 15, 2014 [FF]
- Reduce bug count
- Fix critical bug deferred from 8 and 8u20
- Accessibility complete
- New Controls complete
- Image IOxxx
M3: Oct 20, 2014
- Reduce bug count
- Rich Text Editor prototype
- xxx
...
Overview
Content Tools
ThemeBuilder