jdk11u-dev: Closed for rampdown. Pushes for 11.0.30 after jdk11u-fix-yes approval. Check here for clearance.
jdk11u: Pushes Frozen for release of 11.0.29 after jdk11u-critical-yes approval. Check here for clearance.
Timelines
The release date follows the schedule of Oracle Critical Patch Updates as this is the date embargoed security fixes can be published.
...
- Wednesday, June 4th 2025 : jdk11u-dev forest open (tag: jdk-11.0.29+0)
- Friday, July 25th 2025: First build promotion jdk11u-dev→jdk11u (tag: jdk-11.0.29+1)
- Friday, August 1st 2025: Skipped; no changes.
- Friday, August 8th 2025: Second build promotion jdk11u-dev→jdk11u (tag: jdk-11.0.29+2).
- Friday, August 15th 2025: Third build promotion jdk11u-dev→jdk11u (tag: jdk-11.0.29+3).
- Friday, August 22nd 2025: Fourth build promotion jdk11u-dev→jdk11u (tag:jdk-11.0.29+4).
- Friday, August 29th 2025: Fifth and final build promotion jdk11u-dev→jdk11u (tag:jdk-11.0.29+5). Start of Rampdown phase.
- Friday, September 5th 2025: First jdk11u build promotion (tag: jdk-11.0.29+6). Skipped; no changes.
- Friday, September 12th 2025: First jdk11u build promotion (tag:jdk-11.0.29+7). Skipped; no changes.
- Friday, September 19th 2025: Third jdk11u build promotion (tag:jdk-11.0.29+8)Skipped; no changes.
- Friday, September 26th 2025: Fourth First and final jdk11u build promotion (tag: jdk-11.0.29+96). Frozen for release.
- Tuesday, October 21st 2025: GA; OpenJDK 11.0.29 released (tag: jdk-11.0.29-ga, likely to bejdk-11.0.29+107)
Older releases can be found in the archive.
...