...
Milestone | Task | Who | Effort (expected) | Effort (pessimistic) | Dependency | Target Date | Confidence Level (, , ) | Completed | Comments |
---|---|---|---|---|---|---|---|---|---|
M1 | Setup | ~1 day (M1.1 + 1.2 + 1.3) | ~1 week (M1.1 + 1.2 + 1.3) | When JEP is Funded | Funded: 2013/06/10 notification
| ||||
M1.1 | Staging repository setup | Oracle | Few hours | 1 day | At request of Lead | When JEP is Funded | 2013/06/10 | ||
M1.2 | JIRA CPU and OS updates | Oracle | Few hours | 1 day | After M1.1 | July 2013 | 2013/07/12 | OS value "aix" added. New CPU field unnecessary. The following fields should be updated. OS would have a new field 'aix' with optionally adding version post fix such as 'aix_7.1' or 'aix_6'. The CPU would have a new field 'ppc64'. | |
M1.3 | Hudson instance on staging server | Oracle | Few hours | 1 day | After M1.1 | July 2013 | |||
M2 | Review and approve initial set of changes | ~4 weeks | ~6 weeks | After M1 | 2013/11/28 | The work can happen mostly in parallel, with M2.1 and M2.2 taking roughly the same time to complete as M2.3. | |||
M2.1 | Review changes for a working linux_ppc64 hotspot port | Oracle, SAP, IBM | ~2 weeks | ~3 weeks | After M1.3 | Mid-Late August | 2013/08/20 | The initial 8 changes (1-8) that get a working linux_ppc64 port | |
M2.2 | Review changes for a working aix_ppc64 hotspot port | Oracle, SAP, IBM | ~2 weeks | ~3 weeks | After M1.3 | Mid-Late August | 2013/09/06 | The next set of patches (9-13) to get a working aix_ppc64 port | |
M2.3 | Basic libraries porting effort | Oracle, SAP, IBM | ~2 weeks | ~4 weeks | After M1.3 | Early-October | 2013/11/28 | Enabling the build and basic functionality of the complete JDK on Linux and AIX. | |
M3 | Review and integrate PPC64/C2 and advanced HotSot changes and the remaining AIX class library changes. | ~34 weeks (M3.1 + 3.2 + 3.3 + 3.4) | ~43 weeks (M3.1 + 3.2 + 3.3 + 3.4) | After M2 | None of the sub milestones are dependent on each other, they can happen in any order as the PPC/AIX project members see fit. While the milestones are not dependent on each other, there are resource constraints that will not allow them to happen in parallel. | ||||
M3.1 | HotSpot changes for the PPC64 C2 Port | Oracle, SAP, IBM | ~6 weeks | ~7 weeks | After M2.2 | December | 2013/12/13 | Basic changes for a running C2 Port on PPC64 (~10 changes). | |
M3.2 | Remaining HotSpot changes for PPC64. | Oracle, SAP, IBM | ~12 weeks | ~15 weeks | After M2.2 | February 2014 | 2014/01/22 | Additional C2 and runtime/GC changes which fix remaining problems and improve the performance. | |
M3.3 | Complete and stabilize class library port. | Oracle, SAP, IBM | ~12 weeks | ~15 weeks | After M2.2 | February 2014 | 2014/01/24 | Add class library functionality which is missing on AIX and improve the implementation. | |
M3.4 | Performance evaluation | Oracle, SAP, IBM | ~4 weeks | ~6 weeks | After M3.3 | TBD | All performance criteria resolved | ||
M4 | Stabilization/post integration bug fixing | Oracle, SAP, IBM | ~4 weeks | ~8 weeks | After all milestones | After all milestones | Extended testing on the completed integration will testing and performance regressions resolved | ||
M5 | Final integration | Oracle, SAP, IBM | < 1 week | 1 week | After stabilization period | After stabilization period | Verification of all integrated changes, including a functional satisfaction report by SAP and IBM |
...
Overview
Content Tools
ThemeBuilder